quantitative results and their impact on investment decisions

10.3 Investment Appraisal – Quantitative Techniques and Their Impact on Decision‑Making

Objective

To understand how the quantitative results produced by investment‑appraisal techniques are used to evaluate projects, to compare alternatives, and to inform final investment decisions in line with Cambridge IGCSE/A‑Level syllabus 9609 (10.3).

1. Why Use Quantitative Appraisal?

  • Provides an objective, numerical basis for comparing projects.
  • Shows whether a project is expected to add value to the business.
  • Helps justify capital expenditure to owners, shareholders and other stakeholders.
  • Allows the same decision‑rule to be applied consistently across all proposals.

2. Quantitative Techniques

2.1 Pay‑back Period

Definition: The length of time required for cash inflows to recover the initial investment.

Formula (simple pay‑back):

$$\text{Pay‑back Period} = \frac{\text{Initial Investment}}{\text{Average Annual Cash Inflow}}$$
Quick‑calc box – Cumulative cash‑flow table
YearCash inflowCumulative cash flow
0‑ Initial outlay‑ Initial outlay
1CF₁‑ Initial outlay + CF₁
2CF₂‑ Initial outlay + CF₁ + CF₂
The pay‑back period is the year in which the cumulative cash flow first becomes zero or positive (interpolate if necessary).

Interpretation:

  • Shorter pay‑back periods are preferred when liquidity or risk is a concern.
  • Does not consider cash flows after the pay‑back point and ignores the time value of money.

Limitation: No discounting; unsuitable for long‑term projects.

2.2 Accounting Rate of Return (ARR)

Definition: The return generated on accounting profit relative to the amount invested.

Formula:

$$\text{ARR} = \frac{\text{Average Annual Accounting Profit}}{\text{Average Investment}}\times100\%$$
Quick‑calc box – Average Investment
$$\text{Average Investment} = \frac{\text{Initial Investment} + \text{Salvage Value}}{2}$$ (If there is no salvage value, the denominator is simply half the initial outlay.)

Interpretation:

  • Compare the ARR with the required (hurdle) rate of return.
  • ARR > hurdle → accept; ARR < hurdle → reject.

Limitation: Based on accrual accounting figures; ignores cash flows and the time value of money.

2.3 Net Present Value (NPV)

Definition: The present value of all future cash inflows minus the initial outlay.

Formula (syllabus symbols):

$$NPV = \sum_{t=0}^{n}\frac{C_{t}}{(1+r)^{t}}$$ where \(C_{t}\) = cash flow in period \(t\), \(r\) = required rate of return (discount rate), \(n\) = project life (years).

Interpretation:

  • NPV > 0 → the project adds value; accept.
  • NPV < 0 → the project destroys value; reject.

Limitation: Requires a reliable discount rate; sensitive to forecast errors.

2.4 Internal Rate of Return (IRR)

Definition: The discount rate that makes the NPV of a project equal to zero.

Formula (implicit):

$$0 = \sum_{t=0}^{n}\frac{C_{t}}{(1+IRR)^{t}}$$

Interpretation:

  • IRR > required rate of return → accept.
  • IRR < required rate of return → reject.
  • Unconventional cash‑flow patterns can produce multiple IRRs.

Limitation: Usually found by trial‑and‑error or a financial calculator; multiple IRRs can be confusing.

2.5 Profitability Index (PI)

Definition: The ratio of the present value of future cash inflows to the initial investment.

Formula:

$$PI = \frac{\displaystyle\sum_{t=1}^{n}\frac{C_{t}}{(1+r)^{t}}}{\text{Initial Investment}}$$

Interpretation:

  • PI > 1 → accept.
  • PI < 1 → reject.

Limitation: Shares the same data requirements as NPV; does not show the absolute amount of value added.

3. Qualitative Factors (Syllabus 10.3.4)

Quantitative results must be weighed against non‑financial considerations. Use the checklist below in exam answers.

  • Strategic fit – Does the project support the organisation’s long‑term objectives and core competencies? (e.g., a high‑NPV plant that conflicts with the company’s move towards low‑carbon production may be rejected).
  • Risk profile – Market, technological, regulatory and operational risks that may not be captured in cash‑flow forecasts.
  • Environmental and social impact – Sustainability, corporate social responsibility and stakeholder perception.
  • Legal and ethical considerations – Compliance with legislation, health & safety, and ethical standards.
  • Resource availability – Skills, equipment, and managerial capacity required to implement the project.
  • Opportunity cost of capital – The benefit that could be obtained from the next best alternative use of the funds.

4. Comparative Table of Techniques

Technique Primary focus Considers TVM? Decision rule Key limitation
Pay‑back Period Liquidity & risk No Pay‑back < Maximum acceptable period Ignores cash flows after pay‑back and discounting
ARR Accounting profit No ARR > Hurdle rate Based on accrual figures, not cash
NPV Absolute value creation Yes NPV > 0 Requires a reliable discount rate
IRR Rate of return (relative) Yes IRR > Required rate of return Multiple IRRs possible with unconventional cash flows
PI Relative profitability Yes PI > 1 Same data needs as NPV; no absolute value shown

5. Decision‑Making Process (Paper 4 style)

  1. Identify all viable project proposals.
  2. Gather reliable cash‑flow forecasts and accounting data.
  3. Calculate each quantitative metric (Pay‑back, ARR, NPV, IRR, PI).
  4. Apply the firm’s acceptance criteria (e.g., NPV > 0, IRR > required rate, Pay‑back < policy limit, ARR > hurdle).
  5. Rank projects – usually by NPV (value creation) or by PI when capital is scarce.
  6. Conduct sensitivity / scenario analysis on the top‑ranked projects.
  7. Evaluate qualitative factors using the checklist in section 3.
  8. Prepare a recommendation report for senior management or the board.
Decision flowchart
Flowchart of the investment‑appraisal decision process (from project identification to final recommendation).

6. Sensitivity & Scenario Analysis (Syllabus 10.3.5)

Vary key assumptions to test the robustness of NPV, IRR or PI. The table below shows three common variables.

Scenario Discount rate \(r\) Sales volume (units) Variable cost per unit NPV ($) IRR (%) PI
Base case 10 % 5,000 30 $ 23,400 13.2 1.12
Discount + 1 % 11 % 5,000 30 $ 15,800 12.0 1.08
Sales + 20 % 10 % 6,000 30 $ 38,600 15.1 1.19
Variable cost ‑ 5 $ 10 % 5,000 25 $ 31,200 14.5 1.16

7. Limitations of Quantitative Appraisal

  • Reliance on forecasts – inaccurate estimates can lead to wrong decisions.
  • Intangible benefits (brand value, employee morale, environmental goodwill) are difficult to quantify.
  • Selection of the discount rate may be subjective or biased.
  • Quantitative analysis alone may overlook strategic fit, ethical issues, or long‑term sustainability.

8. Worked Example (All Techniques)

Project data

  • Initial outlay: $200,000
  • Cash inflows: $70,000 at the end of each year for 5 years
  • Accounting profit (before depreciation): $55,000 per year
  • Depreciation (straight‑line): $200,000 ÷ 5 = $40,000 per year
  • Required rate of return (discount rate) \(r\): 10 %
  • Maximum acceptable pay‑back period: 4 years
  • Required ARR (hurdle rate): 12 %

Step‑by‑step calculations

Technique Calculation Result Decision (against criteria)
Pay‑back Period Cumulative cash‑flow table
Year 0‑200,000
Year 1+70,000 → ‑130,000
Year 2+70,000 → ‑60,000
Year 3+70,000 → +10,000
Pay‑back occurs during Year 3.
Interpolating: \(2 + \frac{60,000}{70,000}=2.86\) years.
2.86 years Accept ( < 4 years )
ARR Average Accounting Profit = (Profit + Depreciation) – Depreciation \(=55,000-40,000 = 15,000\) per year
Average Investment = \(\dfrac{200,000+0}{2}=100,000\)
\(ARR = \dfrac{15,000}{100,000}\times100\% = 15\%\)
15 % Accept ( > 12 % )
NPV \[ \begin{aligned} NPV &= -200,000 + \sum_{t=1}^{5}\frac{70,000}{(1.10)^{t}}\\ &= -200,000 + 63,636 + 57,851 + 52,592 + 47,811 + 43,465\\ &= 23,400 \end{aligned} \] $23,400 Accept ( > 0 )
IRR Find \(r\) such that \(\displaystyle\sum_{t=0}^{5}\frac{C_t}{(1+r)^t}=0\).
Using trial‑and‑error (or a financial calculator) gives \(IRR \approx 13.2\%\).
13.2 % Accept ( > 10 % required )
Profitability Index \[ PI = \frac{\displaystyle\sum_{t=1}^{5}\frac{70,000}{(1.10)^{t}}}{200,000} =\frac{223,400}{200,000}=1.12 \] 1.12 Accept ( > 1 )

All quantitative criteria are satisfied. The final recommendation must also weigh the qualitative factors listed in section 3 before seeking board approval.

9. Summary

  • Quantitative techniques translate future cash flows into measurable criteria (Pay‑back, ARR, NPV, IRR, PI).
  • NPV and IRR are the most widely used for value‑based decisions; PI is helpful when capital is limited.
  • Always complement the numbers with qualitative considerations (strategic fit, risk, CSR, legal/ethical issues, resource constraints, opportunity cost).
  • Test the robustness of your results with sensitivity and scenario analysis.
  • Follow the ordered decision‑making process to produce a clear, exam‑style recommendation.

Create an account or Login to take a Quiz

31 views
0 improvement suggestions

Log in to suggest improvements to this note.