network diagrams as tools to plan operations

9.3 Operations Strategy – Operations Planning and Critical‑Path Analysis (CPA)

Learning objectives

  • Construct a network (precedence) diagram for an operation.
  • Carry out forward‑pass and backward‑pass calculations (ES, EF, LS, LF).
  • Determine total float, free float and identify the critical path.
  • Use the diagram to perform Capacity Planning and Analysis (CPA) and discuss its strategic implications (flexibility, innovation, ERP, lean production, benchmarking and quality).
  • Explain how HR, marketing and finance decisions influence the network diagram.

Key concepts

  • Operations planning – deciding what, how, when and where to produce.
  • Capacity Planning and Analysis (CPA) – matching the organisation’s capacity with forecast demand.
  • Network diagram (project/precedence diagram) – visual representation of activities, logical relationships and time required for each.
  • Critical‑Path Analysis (CPA) – technique for calculating the longest sequence of activities (the critical path) and locating slack (float).

How operations decisions influence the network diagram

  • Human‑resources (HR): staffing levels determine the realistic duration of labour‑intensive activities. A shortage of skilled workers lengthens the activity, potentially moving it onto the critical path.
  • Marketing: product‑mix decisions affect the number and type of activities required (e.g., a new colour variant adds a coating step). Forecasted sales volumes from marketing set the demand level used in CPA.
  • Finance: budget constraints may limit the amount of equipment that can be purchased, forcing a longer duration for a bottleneck activity or the use of overtime, both of which alter ES/EF values.

Link to wider operations‑strategy themes (Cambridge syllabus 9.3)

  • Flexibility & innovation: identifying bottlenecks enables process‑innovation (new machinery, automation) or resource re‑allocation that increases volume, delivery‑time or specification flexibility.
  • Enterprise Resource Planning (ERP): modern ERP systems store activity‑duration and resource‑requirement data, automatically generate and update network diagrams, and provide real‑time capacity information for CPA.
  • Lean production: the critical path highlights non‑value‑adding steps; removing or streamlining these steps reduces waste and shortens the overall lead time.
  • Benchmarking: total‑path duration and float values can be compared with industry best‑practice figures to assess relative performance.
  • Quality control & assurance: inspection or testing activities on the critical path must be tightly controlled; any delay directly lengthens the project.

What is a network diagram?

A network diagram shows the logical flow of activities in a process. It is used to:

  • Identify the activities that determine the overall project duration (critical path).
  • Show parallel (concurrent) activities that can be performed at the same time.
  • Calculate earliest start (ES), earliest finish (EF), latest start (LS) and latest finish (LF) times for each activity.
  • Determine total float (TF) and free float (FF) – the amount of time an activity can be delayed without affecting the project finish or the start of a succeeding activity.

Steps to construct a network diagram

  1. List all activities required to complete the operation.
  2. Determine precedence relationships (which activities must finish before others can start).
  3. Assign an estimated duration (days, weeks, hours, etc.) to each activity.
  4. Draw the diagram – use circles or rectangles for activities (nodes) and arrows for dependencies. Number the nodes for easy reference.
  5. Perform the forward pass to obtain ES and EF for every activity.
  6. Perform the backward pass to obtain LS and LF for every activity.
  7. Calculate floats:
    • Total float (TF) = LS – ES = LF – EF
    • Free float (FF) = earliest ES of any immediate successor – EF
  8. Identify the critical path – activities with TF = 0.
  9. Use the diagram for CPA – convert activity times into resource‑hour requirements, spot bottlenecks and evaluate capacity options.

Forward‑pass / backward‑pass calculations

StepFormulaExplanation
Forward pass (left‑to‑right) ES = max(EF of all immediate predecessors)
EF = ES + duration
Gives the earliest time an activity can start and finish.
Backward pass (right‑to‑left) LF = min(LS of all immediate successors)
LS = LF – duration
Gives the latest time an activity can finish/start without delaying the project.

Floats and the critical path

  • Total float (TF) – amount an activity can be delayed without affecting the overall project finish.
  • Free float (FF) – amount an activity can be delayed without affecting the start of any immediate successor.
  • Activities with TF = 0 form the critical path. Any delay on these activities lengthens the whole project.

Using the diagram for Capacity Planning and Analysis (CPA)

CPA consists of three linked stages.

  1. Capacity forecasting – estimate future demand (units per month, quarter, …).
  2. Capacity evaluation – compare forecast demand with the capacity indicated by the network diagram:
    • Critical‑path duration = total time required for one “unit” of output.
    • Convert this duration into capacity‑hours (duration × number of resources required for each activity).
    • Determine how many parallel lines, shifts or overtime slots are needed to meet demand.
  3. Capacity adjustment – decide on actions such as:
    • Adding resources to bottleneck activities (extra machines, staff, overtime).
    • Shortening the critical path by re‑sequencing, process innovation or faster technology.
    • Shifting work to non‑critical activities that have slack.

Scenario (what‑if) analysis

  • What if the duration of a non‑critical activity is reduced? (Check impact on free float.)
  • What if an additional resource is added to a bottleneck? (Re‑calculate the critical path.)
  • What if demand rises by 20 %? (Determine the extra number of parallel lines or shifts required.)

Worked example – Production of a smartphone

Activity Description Duration (days) Predecessor(s)
AComponent procurement4
BAssembly line setup2A
CPhone assembly5B
DSoftware installation3C
EQuality testing2C
FPackaging & dispatch1D, E

1. Network diagram (textual description)

(A) → (B) → (C) → splits to (D) and (E) → both converge to (F). The critical path is shown in bold in the tables below.

2. Forward‑pass (ES / EF)

ActivityES (days)EF (days)
A04
B46
C611
D1114
E1113
F14 * (max of 14 & 13)15

3. Backward‑pass (LF / LS)

ActivityLF (days)LS (days)
F1514
D1411
E14 (F cannot start before 14)12
C11 (minimum of LS of D and E)6
B64
A40

4. Floats

ActivityTotal Float (TF)Free Float (FF)
A00
B00
C00
D00
E1 (LS‑ES = 12‑11)1 (next ES‑EF = 14‑13)
F00

5. Critical path

Activities with zero total float: A → B → C → D → F. Critical‑path duration = 15 days.

6. Capacity evaluation (example)

  • Forecast demand = 30 smartphones per month (≈ 1 unit per day).
  • Critical‑path time for one unit = 15 resource‑days.
  • Required capacity = 30 units × 15 days = 450 resource‑days per month.
  • If the plant works 20 days/month, average daily capacity needed = 450 / 20 = 22.5 resource‑days.
  • Assuming one assembly line provides 5 resource‑days per day, the firm needs at least 5 parallel lines (22.5 / 5 ≈ 4.5 → round up).

7. Scenario analysis

  • What‑if the quality‑testing activity (E) is reduced from 2 days to 1 day?
    New EF for E = 12, LF unchanged at 14 → TF for E becomes 2 days, but the critical path (A‑B‑C‑D‑F) remains 15 days. No capacity gain.
  • What‑if an additional machine cuts the assembly time (C) from 5 days to 3 days?
    Re‑calculate forward pass: EF of C = 9, EF of D = 12, EF of F = 13 → new critical‑path duration = 13 days.
    Capacity requirement falls to 13 × 30 = 390 resource‑days → only 4 parallel lines may now be sufficient.

Advantages of using network diagrams

  • Clear visual of the whole operation and its logical sequence.
  • Identifies the critical path and bottlenecks for targeted improvement.
  • Provides quantitative data (ES, EF, LS, LF, floats) for realistic CPA.
  • Facilitates “what‑if” scenario analysis and supports strategic decisions on flexibility, lean redesign, benchmarking and ERP integration.

Limitations

  • Accuracy depends on the reliability of activity‑duration estimates.
  • Very large or highly complex processes can produce diagrams that are difficult to read.
  • Network diagrams show time but not cost; additional tools (e.g., cost‑benefit analysis) are required for full financial assessment.
  • Quality information must be added explicitly; the diagram itself does not capture defect rates or re‑work.

Exam‑style checklist (what the examiner looks for)

  1. List all activities and their logical order (predecessors).
  2. Assign realistic durations.
  3. Draw a clear network diagram (nodes + arrows, numbered).
  4. Perform the forward‑pass to obtain ES and EF for every activity.
  5. Perform the backward‑pass to obtain LS and LF for every activity.
  6. Calculate total float (TF) and free float (FF) for each activity.
  7. Identify the critical path (activities with TF = 0) and state its total duration.
  8. Convert the critical‑path duration into capacity‑hour requirements and compare with forecast demand.
  9. Discuss at least two capacity‑adjustment options (e.g., add resources, re‑sequence, introduce new technology).
  10. Link the analysis to wider strategic themes – flexibility/innovation, ERP support, lean production, benchmarking and quality control.

Create an account or Login to take a Quiz

29 views
0 improvement suggestions

Log in to suggest improvements to this note.