the meaning, calculation and interpretation of net present value (NPV)

10.3 Investment Appraisal – Net Present Value (NPV)

Learning Objectives

  • Explain why investment appraisal is carried out and the role of NPV within the appraisal process.
  • Calculate NPV using the discounted cash‑flow method, including cost of capital, terminal value and sensitivity analysis.
  • Interpret NPV results and combine them with qualitative/strategic factors to reach a sound business decision.
  • Compare NPV with the basic (non‑discounted) appraisal methods – Pay‑back Period and Accounting Rate of Return (ARR) – and understand their limitations.

10.1 How Investment Appraisal Links to Financial Statements (Syllabus 10.1)

  • Cash‑flow forecasts used in NPV calculations are derived from the statement of cash flows (operating, investing and financing activities).
  • Depreciation (straight‑line, reducing balance, etc.) appears in the profit and loss account and reduces taxable profit, but it is a non‑cash charge – it is added back when preparing cash‑flow statements.
  • Any residual or salvage value at the end of the project is recorded on the balance sheet as a fixed‑asset disposal.

10.2 Impact of Investment Decisions on Ratio Analysis (Syllabus 10.2)

When a project with a positive NPV is accepted, the following ratios are affected:

RatioEffect of a Positive NPV Project
Return on Capital Employed (ROCE)Increases – higher operating profit relative to capital employed.
Gearing (Debt / Equity)May fall if the project is financed from retained earnings; otherwise unchanged.
Liquidity Ratios (Current, Quick)Short‑term impact depends on cash‑flow timing; usually neutral for long‑term projects.
Investment Ratios (Pay‑back, ARR, NPV)Directly reflect the project’s profitability and risk.

10.3 Investment Appraisal – Overview

10.3.1 Concept of Investment Appraisal (Syllabus 10.3.1)

Investment appraisal is a systematic evaluation of the expected costs and benefits of a capital project before any cash is spent. It enables a business to:

  • Allocate scarce capital to the projects that add the most value.
  • Compare alternatives of different sizes, durations and risk profiles.
  • Assess whether a project fits the company’s strategic objectives.

10.3.2 Basic (Non‑Discounted) Methods (Syllabus 10.3.2)

Method What it Measures Formula Key Advantages Key Limitations (Syllabus)
Pay‑back Period Time required for cash inflows to recover the initial outlay. \[ \text{Pay‑back} = \text{Full years before recovery} + \frac{\text{Unrecovered amount at start of final year}}{\text{Cash inflow in final year}} \] Very simple; highlights liquidity risk. Ignores time value of money; ignores cash flows after recovery; no explicit risk assessment.
Accounting Rate of Return (ARR) Average accounting profit as a percentage of average investment. \[ \text{ARR} = \frac{\text{Average Annual Accounting Profit}}{\text{Average Investment}} \times 100\% \] Uses readily‑available accounting data; easy to compute. Based on accounting profit (not cash); ignores timing of cash flows; affected by depreciation method.
Net Present Value (NPV) Present‑value difference between cash inflows and outflows over the whole project life. \[ \text{NPV}= \sum_{t=0}^{n} \frac{C_t}{(1+r)^t} \] Fully incorporates the time value of money; gives a direct estimate of added firm value. Requires an estimate of the discount rate and reliable cash‑flow forecasts.
Worked Example – Pay‑back & ARR

Assumptions:

  • Initial outlay: £100,000
  • Annual cash inflows: £30,000 for 5 years
  • Depreciation (straight‑line): £20,000 per year
  • Tax rate: 0 % (for simplicity)
  1. Pay‑back Period
    Cumulative cash flow after each year: £30k, £60k, £90k, £120k. Pay‑back occurs during year 4 → Pay‑back = 4 years.
  2. ARR
    • Average annual accounting profit = Cash inflow – Depreciation = £30,000 – £20,000 = £10,000.
    • Average investment = (Initial outlay + Residual value) / 2 = (£100,000 + £0) / 2 = £50,000.
    • ARR = (£10,000 / £50,000) × 100 % = 20 %.

10.3.3 Discounted Cash‑Flow Method – Net Present Value (NPV)

Definition (Syllabus 10.3.3)

NPV is the difference between the present value of all expected cash inflows and the present value of all cash outflows associated with a project. A positive NPV indicates that the project is expected to increase the firm’s wealth.

Key Components Required by the Syllabus
  • Cost of Capital / Discount Rate (r) – the required rate of return reflecting the risk of the project and the firm’s financing mix.
  • Cash‑flow Forecasts (Ct) – include:
    • Initial investment (t = 0, negative cash flow).
    • Operating cash inflows/outflows for each year.
    • Tax effects (depreciation shield, tax payments).
    • Salvage / terminal value at the end of the explicit forecast period.
  • Terminal Value – value of cash flows beyond the forecast horizon, usually estimated by a perpetuity growth model: \[ TV = \frac{C_{n+1}}{(r - g)} \] where \(g\) is the assumed long‑term growth rate.
  • Sensitivity / Scenario Analysis – testing how NPV changes when key assumptions (r, cash‑flow amounts, growth rate) vary.
Step‑by‑Step NPV Calculation (Syllabus 10.3.4)
  1. List all cash flows – include the initial outlay, yearly operating cash flows, tax effects and terminal value.
  2. Choose the discount rate – usually the weighted average cost of capital (WACC) or the required rate of return for the project.
  3. Discount each cash flow to its present value: \[ PV_t = \frac{C_t}{(1+r)^t} \]
  4. Sum the present values – the total is the NPV.
  5. Interpret the result using the decision rule (see Section 10.3.5).
  6. Perform sensitivity analysis – recalculate NPV with alternative r, cash‑flow levels or growth rates to assess risk.
Example – Full NPV Calculation Including Terminal Value

Assumptions:

  • Initial machine cost: £120,000 (t = 0)
  • Operating cash inflows: £30,000, £35,000, £40,000, £45,000, £50,000 (t = 1‑5)
  • Salvage value at end of year 5: £20,000
  • Tax rate: 20 %
  • Depreciation (straight‑line, 5 years): £24,000 per year → tax shield = 0.20 × £24,000 = £4,800 each year.
  • Discount rate (WACC): 10 % (r = 0.10)
Year (t)Cash flow before tax (£)Tax (20 %) (£)Net cash flow (£)Discount factor (1/(1+r)^t)PV (£)
0-120,0000-120,0001.000-120,000
130,0006,00024,000 + 4,800 (tax shield) = 28,8000.90926,182
235,0007,00028,000 + 4,800 = 32,8000.82627,101
340,0008,00032,000 + 4,800 = 36,8000.75127,652
445,0009,00036,000 + 4,800 = 40,8000.68327,878
550,000 + 20,000 (salvage)14,00056,000 + 4,800 = 60,8000.62137,757
Total NPV£27,570 (approx.)

Because NPV ≈ £27,600 > 0, the project should be accepted.

Decision Rule (Syllabus 10.3.5)
  • NPV > 0 – Accept; the project adds net wealth.
  • NPV = 0 – The project earns exactly the required return; decision may depend on strategic or qualitative considerations.
  • NPV < 0 – Reject; the project would destroy value.
  • For mutually exclusive projects, choose the one with the highest positive NPV.
Limitations of NPV and How to Overcome Them (Syllabus 10.3.6)
LimitationWhy It MattersSuggested Remedy (Syllabus Requirement)
Estimating the discount rate Cost of capital can be uncertain; a wrong rate skews the NPV. Perform sensitivity analysis using a range of plausible rates (e.g., ±2 %).
Forecasting future cash flows Cash‑flow estimates are inherently uncertain. Use scenario testing (optimistic, most‑likely, pessimistic) and calculate a probability‑weighted NPV.
Terminal value estimation Long‑term growth assumptions heavily influence NPV. Apply a conservative perpetual growth rate (often 2‑3 % for mature economies) and test the impact.
Excludes non‑financial benefits Strategic advantages (brand, market entry, environmental impact) are not captured. Record these as qualitative factors and weigh them alongside the quantitative NPV result.
Assumes cash flows are reinvested at the discount rate May not reflect real reinvestment opportunities. Consider the Modified Internal Rate of Return (MIRR) as a supplementary check (optional).
Qualitative / Strategic Factors (Syllabus 10.3.7)
FactorPotential Impact on Decision
Brand/Image EnhancementMay generate future sales beyond cash‑flow forecast.
Market Entry / ExpansionProvides a foothold in a new market; strategic fit may outweigh a marginal NPV.
Regulatory / Legal RisksCould lead to future costs or restrictions not captured in cash‑flow estimates.
Environmental / Social ResponsibilityImproves reputation; may be required by law or stakeholder expectations.
Technological ObsolescenceRisk that the asset becomes outdated before the forecast period ends.

When NPV is close to zero, these qualitative considerations can tip the decision one way or the other.

10.4 Comparison of All Three Appraisal Methods (Syllabus 10.4)

Method Considers Time Value of Money? Complexity Best Use
Pay‑back Period No Very easy – simple addition Quick liquidity screening; short‑term projects.
Accounting Rate of Return (ARR) No Easy – uses accounting figures Comparing profitability when accounting data are readily available.
Net Present Value (NPV) Yes Moderate – requires discounting and forecasting Full investment appraisal, especially when cash‑flow timing and risk are critical.

10.5 Links to Other Syllabus Areas

  • Risk Management (10.5) – Sensitivity and scenario analysis for NPV are practical applications of risk assessment.
  • Finance & Accounting (10.5.1) – Determining the discount rate uses the cost of capital, which is covered in the finance section.
  • Business Strategy (10.5.2) – Selecting projects based on NPV supports strategic goals such as market expansion, diversification or sustainability.

10.6 Summary Checklist – Calculating & Using NPV

  1. Identify every cash inflow and outflow, including tax effects, depreciation shields, and terminal value.
  2. Determine an appropriate discount rate (WACC or required return).
  3. Discount each cash flow to its present value using \(\frac{C_t}{(1+r)^t}\).
  4. Sum all discounted values – this is the NPV.
  5. Apply the decision rule: Accept if NPV > 0; reject if NPV ≤ 0.
  6. If NPV is borderline, weigh qualitative/strategic factors and perform sensitivity analysis.
Suggested diagram: A cash‑flow timeline showing the initial outlay at \(t = 0\) followed by annual net cash inflows, the terminal value at the final year, and arrows indicating discounting back to present value.

Create an account or Login to take a Quiz

36 views
0 improvement suggestions

Log in to suggest improvements to this note.